The Turichron

Morning brief

Also

Finnish regulator urges a halt to work at Google subsidiary’s two data-center sites

The agency told Tuike Finland Oy on October 6 to stop environment-altering preparation at Muhos and Kajaani by October 23 until impact assessments finish; it is considering enforcement if the company does not comply.

ThereforeEnvironmental review can delay physical expansion even before a data center begins operating.

lvv.fi — Finnish regulator · CNBCCopy link to: Finnish regulator urges a halt to work at Google subsidiary’s two data-center sites